Amendment 14 (FY2016 TIP)
BackAmendment 14 to the FY2016 Transportation Improvement Program (TIP)
Control # | Project Name | Lead Agency | Revision Note |
NE-22203 | Ralston Viaduct | NDOR | Program $260,000 of State- Nebraska funding in FY2016 for ROW and increase NHPP funding for UTIL-CON-CE in FY2016 to $7,840,000 |
NE-22532 | Elkhorn River West | NDOR | Program $201,000 of State-Nebraska funding in FY2016 for ROW and increase STP-State funding in FY2017 to $3,898,000 for UTIL-CON-CE |
NE-22567 | N-31: Schramm Park – US-6 | NDOR | Reprogram $55,000 of State-Nebraska funding to FY2017 for PE-NEPA-FD, program $40,000 of State-Nebraska funding in FY2017 for ROW, and reprogram UTIL-CON-CE phase to FY2018 and increase STP-State funding to $3,994,000 |
NE-22632 | I-680: Mormon Bridge Painting | NDOR | Decrease FY2018 NHPP funding to $5,236,000 for UTIL-CON-CE and program $6,584,000 of State-Iowa funding in FY2018 for UTIL-CON-CE |
NE-22646 | I-80: I-480 to 24th Street | NDOR | Increase State-Nebraska funding for PE-NEPA-FD to $215,000 in FY2016 and reprogram $6,547,000 of State-Nebraska funding in FY2017 for UTIL-CON-CE |
NE-22593 | I-680 / US-6 Bridges | NDOR | Reprogram $295,000 of State-Nebraska funding from FY2016 to FY2020 and decrease FY2021 NHPP funding to $3,065,000 for UTIL-CON-CE |
NE-22634 | US-75 Bridge Approaches, Bellevue | NDOR | Reprogram $1,000 of State-Nebraska funding to FY2017 for PE-NEPA-FD and decrease FY2018 NHPP funding to $1,314,000 for UTIL-CON-CE |
NE-22605 | 2014 Omaha Resurfacing Package | Omaha | Increase FY2016 AC-Conversion to STP-MAPA to $1,935,000 and reduce FY2021 AC-Conversion to STP-MAPA to $1,378,000 |